A sparse set, read four ways#

Units feed buses through the ports they have, and each runs only in the periods it is active. connection lists the ports of each unit and the bus each feeds, and active lists the periods of each unit. Each constraint reads the sets in one way:

  • port_limit reads capacity, a parameter of each unit, at each port.
  • split sums the flows of a unit over its ports, one column of connection.
  • ramp_up steps output along period inside the periods of active.
  • balance sums over every row of connection, grouped by the bus each port feeds.

efficiency and flow list connection under in:, so they exist only where it lists a port, missing: 1 fills only those ports, and a data row for a port that connection does not list is refused. #1019 compares how three designs for sparse sets write this spec.

description: >-
  Units that feed buses through the ports they have, and run only in the
  periods they are active: two sparse sets, read four ways.

dimensions:
  unit: { description: a converter }
  port: { description: an output of a unit }
  bus: { description: a node of the network }
  period: { dtype: int, ordered: true, description: a step of the horizon }

relations:
  connection:
    description: the ports a unit has
    dims: [unit, port]
    missing: absent
  active:
    description: the periods a unit runs in
    dims: [unit, period]
    missing: absent

maps:
  connection:
    bus: { dim: bus, description: the bus a port feeds }

parameters:
  efficiency: { dims: [unit, port, period], in: [connection], missing: 1, description: share of the output a port delivers }
  capacity: { dims: [unit], description: the most a unit produces in a period }
  ramp: { dims: [unit], description: the most a unit's output rises from one period to the next }
  load: { dims: [bus, period], description: demand to be met }

variables:
  output: { dims: [unit, period], in: [active], bounds: { lower: 0 }, description: what a unit produces }
  flow: { dims: [unit, port, period], in: [connection], bounds: { lower: 0 }, description: what a port takes of it }

constraints:
  port_limit:
    description: a port takes no more than the unit's capacity
    dims: [unit, port, period]
    expression: flow <= capacity
  split:
    description: the ports of a unit take what it produces
    dims: [unit, period]
    expression: sum(flow, over=port) == output
  ramp_up:
    description: output rises by at most the ramp from one active period to the next
    dims: [unit, period]
    expression: output - shift(output, along=period, offset=1) <= ramp
  balance:
    description: what the ports deliver to a bus meets its load
    dims: [bus, period]
    expression: sum(efficiency * flow, over=[unit, port], by=connection[bus]) >= load

objective:
  sense: minimize
  expression: sum(output)

Units that feed buses through the ports they have, and run only in the periods they are active: two sparse sets, read four ways.

Sets#

Symbol Meaning
\(\mathcal{B}\) index \(b\) — bus with \(\mathrm{bus}: \mathrm{connection} \to \mathcal{B}\) — a node of the network
\(\mathcal{T}\) index \(t\) — period with \(\mathrm{active} \subseteq \mathcal{T} \times \mathcal{U}\), active is absent where the data has no row — a step of the horizon
\(\mathcal{O}\) index \(o\) — port with \(\mathrm{connection} \subseteq \mathcal{O} \times \mathcal{U},\ \mathrm{bus}: \mathrm{connection} \to \mathcal{B}\), connection is absent where the data has no row — an output of a unit
\(\mathcal{U}\) index \(u\) — unit with \(\mathrm{active} \subseteq \mathcal{T} \times \mathcal{U},\ \mathrm{connection} \subseteq \mathcal{O} \times \mathcal{U},\ \mathrm{bus}: \mathrm{connection} \to \mathcal{B}\), active is absent where the data has no row, connection is absent where the data has no row — a converter

Parameters#

Symbol Meaning
\(\mathrm{capacity}\) capacity over \(\mathcal{U}\) — the most a unit produces in a period
\(\mathrm{efficiency}\) efficiency over \(\left( o,\ u \right) \in \mathrm{connection},\ t \in \mathcal{T}\), \(1\) where the data has no row — share of the output a port delivers
\(\mathrm{load}\) load over \(\mathcal{B} \times \mathcal{T}\) — demand to be met
\(\mathrm{ramp}\) ramp over \(\mathcal{U}\) — the most a unit's output rises from one period to the next

Variables#

Symbol Meaning
\(\mathit{flow}\) flow over \(\left( o,\ u \right) \in \mathrm{connection},\ t \in \mathcal{T}\) — what a port takes of it
\(\mathit{output}\) output over \(\left( t,\ u \right) \in \mathrm{active}\) — what a unit produces

Variable domains#

flow

\[ \mathit{flow}_{t,o,u} \ge 0 \qquad \forall\, \left( o,\ u \right) \in \mathrm{connection},\ t \in \mathcal{T} \]

output

\[ \mathit{output}_{t,u} \ge 0 \qquad \forall\, \left( t,\ u \right) \in \mathrm{active} \]

Objective#

\[ \min \sum_{t \in \mathcal{T},\ u \in \mathcal{U}} \mathit{output}_{t,u} \]

Subject to#

balance

\[ \sum_{o \in \mathcal{O},\ u \in \mathcal{U} \,:\, \mathrm{bus}(o,\ u) = b} \mathrm{efficiency}_{t,o,u} \cdot \mathit{flow}_{t,o,u} \ge \mathrm{load}_{b,t} \qquad \forall\, b \in \mathcal{B},\ t \in \mathcal{T} \]

port_limit

\[ \mathit{flow}_{t,o,u} \le \mathrm{capacity}_{u} \qquad \forall\, t \in \mathcal{T},\ o \in \mathcal{O},\ u \in \mathcal{U} \]

ramp_up

\[ \mathit{output}_{t,u} - \mathit{output}_{t - 1,u} \le \mathrm{ramp}_{u} \qquad \forall\, t \in \mathcal{T},\ u \in \mathcal{U} \]

split

\[ \sum_{o \in \mathcal{O}} \mathit{flow}_{t,o,u} = \mathit{output}_{t,u} \qquad \forall\, t \in \mathcal{T},\ u \in \mathcal{U} \]